Navi Mumbai: Centre Orders Probe Into Environmental Violations By CIDCO In PMAY Projects Near Mangroves

Navi Mumbai: Centre Orders Probe Into Environmental Violations By CIDCO In PMAY Projects Near Mangroves

The Centre has asked the Maharashtra Government to probe into the alleged environmental violations in the execution of the Prime Minister Awas Yojana (PMAY) by the state-owned City and Industrial Development Corporation (CIDCO) in Navi Mumbai.

FPJ News ServiceUpdated: Monday, September 02, 2024, 11:52 PM IST
article-image
Satellite picture_Kharghar_PMAY_Touching Mangroves | File Image

Navi Mumbai: The Centre has asked the Maharashtra Government to probe into the alleged environmental violations in the execution of the Prime Minister Awas Yojana (PMAY) by the state-owned City and Industrial Development Corporation (CIDCO) in Navi Mumbai.

This follows environment watchdog NatConnect Foundation’s complaint to the Prime Minister that the construction is taking place “dangerously” close to mangroves and the Panvel creek disregarding the global concerns over the rising sea levels.

NatConnect Foundation’s concern is that the 10,000 people and the scores of small businessmen, who will be accommodated at Kharghar project, will permanently be under the threat of tidal wave attacks.

“At a time when we ought to be working on disaster mitigation measures, we are building multi-storeyed residential and commercial complexes close to the sea,” NatConnect Foundation director B N Kumar regretted and observed that the town planners do not seem to learn any lessons from unseasonal floods and the monsoon havoc along coastal areas in particular.

CIDCO confirmed to the media that as many as 17 towers would come up at Khaghar alone, Kumar said this is an invitation to disaster. Kumar had filed his complaint on the PM Office Public Grievances (PMOPG) website.

The Union Ministry of Environment, Forest and Climate Change (MoEF&CC) has now asked the Maharashtra Coastal Zone Management Authority (MCZMA) to study the issue and report back.

MoEF&CC scientist in CRZ section Dr Raghavan P who signed the letter dated August 23, pointed out that the states and the union territories have been authorised to enforce and monitor the Coastal Regulation Zone provisions under the Environment Protection Act- 1986.

He, therefore, asked the member secretary of the MCZMA to examine the extent of the “serious violations” in the execution of the PMAY in Navi Mumbai.

The PMAY projects, particularly in Mansarovar and Kharghar areas, have come up in proximity of mangroves, mudflats and inter-tidal wetlands, NatConnect said in its complaint.

The compound wall of the Kharghar project on the northern side of the railway station almost touches the mangroves with the distance between the sea plants and the project being 8 metres to 25 metres, the NGO said citing google earth maps.

“This is in violation of both the central and state clearances given for the projects,” it said. The environmental clearance summary clearly stated that no mangroves will be affected during construction of the entire project and that the 50-meter buffer line has to be maintained. There is supposed to be thick vegetation of tall trees with foliage along the buffer line to mitigate any fugitive dust emission etc. towards the mangrove area, NatConnect said.

The 143rd meeting of the Maharashtra Coastal Zone Management Authority held on February 4, 2020 clearly noted that the projects were partly under CRZ1 and hence CIDCO was prohibited from doing any construction in the 50 mtr mangrove buffer zone and to maintain a 100 mtr CRZ setback for the creek.

But the Kharghar project presents a worrying scene as the PMAY buildings have come up in the danger line, Kharghar-based activist Joyoti Nadkarni said "The compound wall will push the high tide line towards the Panvel creek and this is bound to cause flooding in other areas as water finds its own course and does not go by CIDCO walls," she said.

The environmental clearances have been given post the state mangrove cell visits and with conditions that the mangrove zones should not be impacted.

Pointing out that the tax-payers’ hard earned money goes as subsidies into the PMAY project, Nadkarni said it cannot be spent on anti-environmental projects.

RECENT STORIES

Mumbai Rains: City Witnesses Drizzles & Cloudy Skies; IMD Says Light Showers To Continue For Next 24...

Mumbai Rains: City Witnesses Drizzles & Cloudy Skies; IMD Says Light Showers To Continue For Next 24...

Virar Murder: Man Stabs Wife To Death Over Suspicion About Her Character; Accused Arrested In Kalyan

Virar Murder: Man Stabs Wife To Death Over Suspicion About Her Character; Accused Arrested In Kalyan

Thane: Shiv Sena Removes 2 Office-Bearers For Disrespecting CM Eknath Shinde's Mentor Anand Dighe By...

Thane: Shiv Sena Removes 2 Office-Bearers For Disrespecting CM Eknath Shinde's Mentor Anand Dighe By...

Mumbai: 25-Yr-Old Man Dies After He Rams Bike Into Dumper At BKC's Nabard Junction; 'Had Gone To Buy...

Mumbai: 25-Yr-Old Man Dies After He Rams Bike Into Dumper At BKC's Nabard Junction; 'Had Gone To Buy...

Mumbai-Doha IndiGo Flight Delayed For Over 5 Hours; 'Made To Wait In Holding Area Without Food &...

Mumbai-Doha IndiGo Flight Delayed For Over 5 Hours; 'Made To Wait In Holding Area Without Food &...