Jammu and Kashmir: India's long-awaited cable-stayed rail bridge on Anji river finally nears completion
The Anji bridge is being constructed in Reasi district of Union territory of Jammu and Kashmir under the most challenging Udampur-Srinagar-Baramulla-Rail Link (USBRL) Project of Indian Railways.
Country's first cable stayed railway bridge will be ready by May 2023 on Anji river in Jammu and Kashmir. It will look like Worli-Bandra sea link of Mumbai in appearance.
๐๐ฟ๐ถ๐ฑ๐ด๐ฒ ๐ฏ๐ฒ๐ถ๐ป๐ด ๐ฐ๐ผ๐ป๐๐๐ฟ๐๐ฐ๐๐ฒ๐ฑ ๐ผ๐ป ๐๐ป๐ท๐ถ ๐ฟ๐ถ๐๐ฒ๐ฟ ๐ถ๐ป ๐ฅ๐ฒ๐ฎ๐๐ถ ๐ฑ๐ถ๐๐๐ฟ๐ถ๐ฐ๐
The Anji bridge is being constructed in Reasi district of Union territory of Jammu and Kashmir under the most challenging Udampur-Srinagar-Baramulla-Rail Link (USBRL) Project of Indian Railways. The bridge is about 80 km by road from Jammu.
"Anji Bridge is country's 'first cable-stayed bridge' of Indian Railways connecting Katra and Reasi in Jammu and Kashmir. The bridge is a part of the national project of Udhampur-Srinagar- Baramulla Rail Link (USBRL) Project," said an official of Indian railways. The official added that the bridge is located in the young fold mountains of Himalayas having extremely complex, fragile and daunting geological features in the form of faults, folds and thrusts and besides seismic proneness of the region. Detailed site specific investigations were carried out by IIT, Roorkee and IIT, Delhi. Slopes of the mountain supporting one foundation of main span have been stabilised by a special hybrid foundation on Katra end due to space constraints.
๐๐ฟ๐ถ๐ฑ๐ด๐ฒ ๐ฑ๐ฒ๐๐ถ๐ด๐ป ๐ฎ๐ป๐ฑ ๐๐ฝ๐ฒ๐ฐ๐ถ๐ณ๐ถ๐ฐ๐ฎ๐๐ถ๐ผ๐ป๐
The major portion of the bridge works, including Main Pylon with 40 meter deep Hybrid foundation, Central Embankment and Ancillary Viaduct, were carried out on Srinagar end. Total length of the bridge is 725.5 meter. Considering ease of construction and typical site conditions, bridge has been divided into 4 parts.
"The total length of Bridge is 725 meter consisting of Main Bridge having the length of 473.25 metres , ancillary viaduct of 120 metres length, approach Bridge of 38 meters on Katra end and the central embankment of 94.25 metres length," said an official of Northern railway while explaining the project.
"The main Bridge over Anji is a Cable Stayed Bridge with a total length of 473.25m consisting of main span of 290 meter," he said.
Anji river Bridge connects tunnel number two and three on the Katra-Banihal Section of the Udhampur. This Bridge has a single main pylon of height 193 meter from the top of foundation, standing at a height of 331 metres above the river bed.
According to railway officials, It is an asymmetrical cable-stayed bridge balanced on the axis of a central pylon. The total deck width of Bridge is 15 meter. The Bridge has support of 96 cables having cable length varying from 82 meter to 295 m. The micro piles of 40 metre depth all around the circumference of 20 metre hybrid well foundation were used in Main Pylon construction. The Bridge shall carry a single railway line plus a 3.75 meter wide service road. There is a 1.5 meter meter wide footpath on each side of the deck with an overall width of 15 meter.
๐๐ฟ๐ถ๐ฑ๐ด๐ฒ ๐ฐ๐ฎ๐ป ๐ต๐ฎ๐ป๐ฑ๐น๐ฒ ๐ต๐ฒ๐ฎ๐๐ ๐๐๐ผ๐ฟ๐บ๐ ๐ฎ๐ป๐ฑ ๐ฒ๐ ๐ฝ๐น๐ผ๐๐ถ๐ผ๐ป
The Bridge has been designed to handle heavy storms of strong winds. The design wind speed considered is 213 Kmph. State of the art Tower crane (imported from Spain) of 40 tons capacity with extendable height up to 205 meters is being used for enhancing the construction activities at heights up to 193 meter. The Bridge will also have an integrated monitoring system by means of numerous sensors installed at various locations on the bridge.
Estimated total cost of the bridge will around Rs 400 crores .The bridge will be able to carry load of trains at the speed of 100 kmph.
Asked about the codel life of the bridge, an official said, "The codal life of this bridge is 120 year, which can be able to bear the explosion of 40 kg explosive materials. Apart from that, the bridge can easily handle the winds up to the speed of 213 kmph."
๐๐ฎ๐ฟ๐ด๐ฒ ๐ป๐ผ ๐ผ๐ณ ๐๐ฒ๐ป๐๐ผ๐ฟ๐ ๐๐ผ ๐บ๐ผ๐ป๐ถ๐๐ผ๐ฟ ๐ต๐ฒ๐ฎ๐น๐๐ต ๐ผ๐ณ ๐ฏ๐ฟ๐ถ๐ฑ๐ด๐ฒ
"Site specific Earthquake parameters studies were carried out by Department of Earthquake Engineering, Indian Institute of Technology, Roorkee to define the seismo-tectonic framework for the region" he said.
"Due to the importance of the bridge, a large number of sensors shall be placed on it to monitor structural health of the bridge during service. Wind tunnel tests: Because of the long span and the deep valley, tests in the Wind Tunnel were also conducted, in order to evaluate the aerodynamic actions (static aerodynamic coefficients) and to investigate about aero elastic phenomena (galloping, flutter and vortex shedding)" he further added.
RECENT STORIES
-
Bombay HC Raps Police For Ignoring Magistrate's Order To File FIR In Suicide Case, Imposes โน20,000... -
Mumbai: 43-Year-Old Man Sentenced To Life For Wifeโs Murder Despite Son Turning Hostile As Witness -
Sachin Kurmi Murder Case: 'Will Immolate Myself If Masterminds Not Arrested,' Says Kurmi's Widow -
โI Cried, He Did Approach Me Like Thatโ: Bigg Boss 18โs Alice Kaushik On Boyfriend Kanwar... -
Mumbai: Ex-MP Gopal Shetty Detained For Stopping BMC Workers From Disconnecting Water Supply In...